Boston Green Line Riders Face Nine Days of Shuttles
The MBTA will close sections of the Green Line from November 7 through 15 to replace century-old signals and upgrade station accessibility.
By Lauren Foster ·

Commuters in Boston will need to add time to their trips starting next week. The Massachusetts Bay Transportation Authority (MBTA) is closing portions of the Green Line for nine consecutive days, from November 7 through November 15. During this period, riders must rely on shuttle buses and alternative rail connections. The agency says these closures allow workers to complete complex upgrades that require 24-hour access to the tracks.
The Green Line signal system dates back to the late 1800s. The current infrastructure is as old as the tunnel it occupies. Previous administrations postponed replacing this equipment due to the complexity of the work. The MBTA states it is now prioritizing these upgrades to improve reliability. Crews have already installed 56 miles of new signaling cable in the central tunnel. During this November window, they plan to add 16 miles of signal cable and one mile of fiber optic cable.
Work will focus on specific stations in the central tunnel. At Copley, crews will finish connecting signals and track circuits. They will also begin testing the modernized system. Between Park Street and Boylston, workers will install signal cable on eastbound tracks. At Government Center, crews will place signal cable in all Green Line track areas within the station. The new system aims to provide better train detection and more consistent spacing.
The project also advances accessibility on the C Branch. The MBTA is upgrading seven above-ground stations that are currently inaccessible to riders with disabilities. These locations include Englewood Avenue, Dean Road, Tappan Street, the consolidated Fairbanks Street/Brandon Hall station, Summit Avenue, Saint Paul Street, and Hawes Street. When complete, all stations on this branch will be accessible. During the shutdown, crews will install platform edges, curbing, and lighting foundations at Summit Avenue and Hawes Street. They will also remove existing inbound platforms and shelters at those two stops.
The accessibility project is designed in two phases. The first phase installs eight-inch platforms to comply with ADA standards for the current fleet of Green Line vehicles. The second phase will occur once the MBTA fully transitions to the new Type 10 Green Line cars. That future step involves raising platforms by six inches to a total height of 14 inches. This adjustment allows for level boarding with the new trains. The MBTA notes that the current fleet’s bi-fold doors would interfere with higher platforms, necessitating the staged approach.
Beyond signals and accessibility, crews will complete other maintenance tasks during the closure. Work includes replacing ties and ballast at Symphony station. Technicians will upgrade radio systems and install security cameras at Park Street, Downtown Crossing, and Broadway. The agency will also perform general maintenance in the pump room at Commonwealth Avenue. Additionally, crews will conduct visual inspections of tunnel structures and replace timbers along the E Branch.
Riders can use free shuttle buses and specific rail connections to navigate the service changes. On the B Branch, shuttles will run between Babcock Street and Back Bay. On the C Branch, shuttles will operate between Cleveland Circle and Back Bay, though service will not stop at Saint Mary’s Street, Kent Street, or Brandon Hall. On the D Branch, shuttles will connect Kenmore to Back Bay. Route 39 bus service will replace the E Branch between Heath Street and Back Bay. All shuttle buses are accessible, though weekday service may use lift-equipped coach-style buses while weekends will feature ramp-equipped low-floor buses.
The Worcester Commuter Rail Line will be fare-free between South Station, Back Bay, and Lansdowne during this period. Riders traveling beyond Lansdowne or on other commuter lines must pay regular fares. The MBTA advises riders to budget extra time for their commutes. For example, a trip from Cleveland Circle to Park Street should allow for at least 25 additional minutes. Complete details and real-time updates are available at MBTA.com/GreenLine.