Duke Energy Rates Rise 3.7% After NC Utilities Commission Approval

Regulators approved new electricity prices, lowered the utility's rate of return, and created specific fees for large data centers.

By Samuel Hayes ·

Illustration for: Duke Energy Rates Rise 3.7% After NC Utilities Commission Approval
Illustration generated for this article, not a news photograph.

Duke Energy Carolinas customers will see an average electricity rate increase of 3.7 percent over the next two years, according to the utility. The North Carolina Utilities Commission approved the new rates after months of public testimony and review.

The commission accepted the utility’s concession to lower its target rate of return. Duke originally filed a request to raise its annual revenue by $595 million and increase its return to 10.95 percent. Following public backlash, the company reduced its request twice, first to 10.48 percent and finally to 9.8 percent. This final figure is lower than the return Duke currently earns.

State regulators also approved the utility’s plan to keep its coal fleet operational through 2040. The order authorized investments in new nuclear reactors at the W.S. Lee and Shearon Harris power plants in North Carolina.

The new rate order establishes distinct pricing for data centers to address their specific impact on the grid. The Commission noted that these facilities require power 90 percent of the time, a demand profile unlike other industrial customers. The order cites the scale and speed of data center growth as a source of unique risk to the electrical system.

Duke Energy Carolinas has signed service contracts to supply 6.7 gigawatts of power to high-demand industrial customers. Data centers account for 92 percent of that contracted capacity. The utility estimates that large data centers will represent 9.2 percent of peak demand for Duke Energy Carolinas by 2035.

The commission ordered Duke to track data center service costs as a separate customer class. This measure is intended to mitigate risks for other ratepayers. The order states that these risks must be borne by the data centers imposing them or by existing ratepayers who did not cause them.

The new rates apply to new and existing data centers that require more than 50 megawatts of power. The order includes a new contract term called the Stranded Generation Charge, which allocates the cost of building new power plants to those data centers.

More Business · Greensboro news · Scam Watch · Report a business · Got a Story?